INEEL Advanced Test Reactor
(ATR) Accidents 1991 to 1999
1991
May
20; Advanced Test Reactor fuel element fell from handling tool to water storage
canal floor.
June
4; ATR reactor scrammed due to under
voltage to coolant pump.
Aug.13; ATR reactor scrammed due to loss of power
to coolant pump.
Oct.14; ATR reactor scrammed due to low coolant
pressure caused by malfunctioning
temperature control valve.
Oct.16; ATR reactor scrammed again due to low
coolant pressure caused by another
malfunctioning temperature control valve.
1992
Jan.16; Advanced Test Reactor spilled 350 gallons
of sulfuric acid into the "cold" waste pond;
Apr.
12; Advanced Test Reactor was scrammed
when a diesel generator supply power failed;
1993
Jan.4; Advanced Test Reactor scrammed. During a lC-W loop experiment, a scram occurred
due to loss of flow signal because of an operator
error. The operator did not properly
follow the procedure and a reset button was depressed which caused
the loop pumps to turn off and
the reactor scrammed.
Sept.
8; A damaged C cell battery was found in the ATR reactor vessel outside of the
core region and
removed;
a thorough inspection of the vessel revealed no other debris and the vessel was
closed up.
Sept.
13; Crushed parts of a flashlight were found inside the ATR reactor vessel, but
outside the core
region
and no debris was found on the fuel.
Detailed inspections were conducted including
the
use of an underwater camera video system, but other missing flashlight parts were
not
found. Reactor operation was delayed for more than
two days and in-vessel inspections will
be performed following
each nuclear re_qualification testing event.
1994
April
4; During refueling of the Advanced
Test Reactor, 19 workers received internal radiation
exposure caused by underwater
control rod cutting operations in preparations for disposal.
Workers
using a remote control saw were cutting through a control rod of hafnium and
aluminum
and either the saw arced or hit the hafnium which got into bubbles of hydrogen
and
rose
to the surface of the pool. The highest dose was 2 mRem. Hafnium has a half life of 45
days. The facility was evacuated. OCAW union said exposure was 1.3 REM and
internal uptake of 96 microcurie of
hafnium-181.
1995
July
3; Several pipefitters working at the Advanced Test Reactor were exposed to
50,000 counts per
minute by over a dozen isotopes because their anti-contamination
(anti-c) clothing provided
inadequate protection in the work environment. In another event, a DOE Environmental
Health Representative was contaminated while conducting an
inspection of the check valve
work that was the
subject of previous pipefitter contamination.
In both cases the Pro-Tech
2000 anti-c clothing did
not prevent the migration of graphite particles through the material
or protect individuals
during bending, kneeling, extreme temperatures, or presence of
contaminated liquids.
Aug.
24; The Advanced Test Reactor Emergency Fire Water Injection System would be
rendered
inoperable during a design basis earthquake. The purpose of the injection system is to
pump
water into the
reactor core to prevent irradiated fuel elements from being uncovered in the
event of a loss-of-coolant accident or
a complete loss of coolant flow during an earthquake.
1997
Feb.24; Advanced Test Reactor
accident resulted in 410 pounds of Freon when a scaffold fell on and broke a
chiller unit line. Operators attempting
to use self-contained breathing apparatus found five to be unusable. Freon, according to NIOSH is immediately
dangerous to life or health in concentrations as low as 2 ppm.
Feb.27; DOE imposed $25,000
civil penalty on Lockheed Martin Idaho Technologies under the Price
Anderson Act for multiple failures to maintain radiation
exposures as low as reasonably achievable.
Mar.1;
A Test Reactor Area Technician received a whole body neutron exposure of 1865
millirem
the month of April and the source of the exposure could not be
determined.
Mar.13; Two cesium-137 sources
containing 27.5 mCi and 12 mCi with a potential dose rate of 111 mrem/hr were
lost and a search was unable to determine their location.
April 27; Advanced Test Reactor
spent fuel element fell off handling device during transfer from reactor to
storage pool.
Oct 25; Advanced Test Reactor
operators discover five holes in gas-tight reactor confinement boundary (during
operations) that subcontractors had left unfilled. This breached the reactor gas-tight confinement boundary. A similar event occurred on December 16,
1996 at the same location.
1998
Jan 12; The Advanced Test
Reactor at the Test Reactor Area had an uncontrolled shutdown after a secondary
coolant line system piping leaked.
1999
Feb. 17; Advanced Test Reactor
operators found that a flux trap target capsule holder assembly had been
rotated 90 degrees from its intended position since 1994. Miss orientation of
the targets could have caused a variation of the neutron flux peaking within the flux trap resulting in operating
the advanced test reactor outside its safety authorization basis.
March 22; Advanced Test Reactor
crane dropped a 400 pound irradiated inpile tube assembly being lifted from the
reactor core and narrowly missed hitting a worker. The uncontrolled fall damaged the storage well and docking plate.